TMS were instructed to install a gabion wall alongside the bridge abutment to provide scour protection and bank stabilisation. The bed was leveled with a long reach machine from the shore. TMS then laid a layer of stone ready to install gabion matresses. TMS divers installed all of the lower baskets and mattresses. Once the baskets were up out of the water the top line of baskets were finished off conventionally. All of the baskets were hand filled and faced with stone. Once the baskets were installed we back-filled with clean stone and type one material to the top, ready for top soil.
TMS Ltd
22 December 2010
Leven Bridge Bank Stabilisation and Scour Protection.
Lizard RNLI Slipway Build
TMS divers have been installing the sub-sea sections of the RNLI'S new lifeboat slipway at Lizard Point Cornwall. TMS were contracted for a period of three months to assist Nuttall John Martin Construction in assembling and positioning the 23 tonne steel pre-fabricated sections that make up the length of the slipway. This involved positioning concrete transoms on top of the already installed tubular piles, Positioning the steel sections on top of the transoms to the correct line and level and then grouting the sections when finally in position. These works are essential for the continuing modernisation of the RNLI and will now enable the Lizard Point Lifeboat Station to be equipped with the new state of the art "Tamar" class lifeboat. Click on the link to see TMS divers at work on ITV News! http://www.itv.com/westcountry-west/lifeboats-for-the-lizard77953/ .......
Left: The site at Lizard Point.
Below: TMS diver entering the water.
2 November 2010
Polperro Sub-Sea Pipeline.
TMS Ltd deployed an 8 man HSE dive team with 2 divers in the water at one time. TMS were instructed to lay an outfall pipe from the shore, 350 metres to sea, in depths of water up to 19 metres. All of the diving works were carried out from the deck of the "Will Challenge". The pipeline is part of £5.5m sewer outfall for South West Water. You can see a live web cam by clicking here of the current contract works.
Preston Park Jetty
Preston Park at Stockton-on-Tees
TMS constructed a Jetty for Birse Civils. TMS installed 6 tubular piles with conventional means of piling. A large steel frame fabricated by TMS was installed on top of the piles and fully welded. A Balau 200mm x 100mm hard wood deck with galvanised hand rails all round was laid. There were non-slip boards laid down and 10 ton bollards bolted down for the docking of large passenger vessels. Heavy duty "D" fendering was installed on the outside of the jetty. TMS laid all new paths for disabled access and carried out fencing works and some gabion basket revetment repairs to the river banks.
TMS constructed a Jetty for Birse Civils. TMS installed 6 tubular piles with conventional means of piling. A large steel frame fabricated by TMS was installed on top of the piles and fully welded. A Balau 200mm x 100mm hard wood deck with galvanised hand rails all round was laid. There were non-slip boards laid down and 10 ton bollards bolted down for the docking of large passenger vessels. Heavy duty "D" fendering was installed on the outside of the jetty. TMS laid all new paths for disabled access and carried out fencing works and some gabion basket revetment repairs to the river banks.
Subscribe to:
Posts (Atom)